Twin council tower blocks
East Midlands · 2024 to 2025
The work
Phase-one fire stopping through the common areas and risers of both towers, plus new riser openings with lintels and fire-rated access doors on the top floors. Before anyone drilled, our asbestos team removed the asbestos-containing coatings under notifiable non-licensed controls.
Outcome
477 and 398 locations recorded, photographed and rated at 60 minutes, with full-building reports issued. The fire works never waited on a second contractor.
Services used
Related projects
17-storey council tower
A 226-location survey report and a 43-day phase-one programme: asbestos survey, two days' mobilisation and 36 days on the tools, working top down at 1.5 days per floor.
View project →14-storey residential tower
A floor-by-floor report with “installed” against every pin, ready for the landlord's building safety case.
View project →Five-level residential block
An action-required schedule the landlord could price, phase and put in front of the fire authority.
View project →