17-storey council tower
East Midlands · 2024
The work
Every fire-stopping breach in the common areas was pinned, photographed and given a remedy, ground to 17th floor. Our surveyors ran a targeted asbestos survey first and found textured coating above the false ceilings, so the fire team knew exactly what it was drilling into.
Outcome
A 226-location survey report and a 43-day phase-one programme: asbestos survey, two days' mobilisation and 36 days on the tools, working top down at 1.5 days per floor.
Services used
Related projects
Twin council tower blocks
477 and 398 locations recorded, photographed and rated at 60 minutes, with full-building reports issued. The fire works never waited on a second contractor.
View project →14-storey residential tower
A floor-by-floor report with “installed” against every pin, ready for the landlord's building safety case.
View project →Five-level residential block
An action-required schedule the landlord could price, phase and put in front of the fire authority.