Five-level residential block
East Midlands · 2025
The work
A floor-by-floor survey: head-of-wall joints needing intumescent beads, foam-filled voids to cut out and replace with batt and mastic, unsealed penetrations, missing pattresses and pipe collars. Voids we couldn't reach were listed, not guessed.
Outcome
An action-required schedule the landlord could price, phase and put in front of the fire authority.
Services used
Related projects
17-storey council tower
A 226-location survey report and a 43-day phase-one programme: asbestos survey, two days' mobilisation and 36 days on the tools, working top down at 1.5 days per floor.
View project →Twin council tower blocks
477 and 398 locations recorded, photographed and rated at 60 minutes, with full-building reports issued. The fire works never waited on a second contractor.
View project →14-storey residential tower
A floor-by-floor report with “installed” against every pin, ready for the landlord's building safety case.