Tenanted council homes
Yorkshire · 2022 to 2024
The work
Full and targeted refurbishment surveys of 1950s brick and non-traditional homes ahead of kitchen, bathroom, roofing and rewiring programmes: booked by appointment, two surveyors, sample points sealed, analysis by a UKAS-accredited laboratory.
Outcome
Reports quality-checked and issued in days, so the trades could plan around the findings.
Services used
Related projects
17-storey council tower
A 226-location survey report and a 43-day phase-one programme: asbestos survey, two days' mobilisation and 36 days on the tools, working top down at 1.5 days per floor.
View project →Twin council tower blocks
477 and 398 locations recorded, photographed and rated at 60 minutes, with full-building reports issued. The fire works never waited on a second contractor.
View project →14-storey residential tower
A floor-by-floor report with “installed” against every pin, ready for the landlord's building safety case.