Tenanted housing estate
North East · 2024 to 2025
The work
Licensed removal of asbestos insulating board from external stores across a tenanted estate, plus textured coatings, floor tiles and window mastics ahead of planned works, with residents out for each removal or kept safely in.
Outcome
Eleven licensed removals in eleven working days in the first month, and every home cleared by an independent UKAS-accredited analyst.
Services used
Related projects
17-storey council tower
A 226-location survey report and a 43-day phase-one programme: asbestos survey, two days' mobilisation and 36 days on the tools, working top down at 1.5 days per floor.
View project →Twin council tower blocks
477 and 398 locations recorded, photographed and rated at 60 minutes, with full-building reports issued. The fire works never waited on a second contractor.
View project →14-storey residential tower
A floor-by-floor report with “installed” against every pin, ready for the landlord's building safety case.