Live pharmaceutical site
Republic of Ireland · 2023
The work
An HSG264 management survey of the original building on an operating laboratory site: offices, labs, boiler room, production areas, loft and externals, with samples analysed by a UKAS-accredited laboratory.
Outcome
Six asbestos-cement items identified and scored, with repair and removal areas marked up on the plans for the follow-on works.
Services used
Related projects
17-storey council tower
A 226-location survey report and a 43-day phase-one programme: asbestos survey, two days' mobilisation and 36 days on the tools, working top down at 1.5 days per floor.
View project →Twin council tower blocks
477 and 398 locations recorded, photographed and rated at 60 minutes, with full-building reports issued. The fire works never waited on a second contractor.
View project →14-storey residential tower
A floor-by-floor report with “installed” against every pin, ready for the landlord's building safety case.
View project →