Ceiling compartmentation
Housing association offices
Yorkshire · 2024
2offices
7days each
The work
Ceilings overboarded with 15 mm fire-rated plasterboard and every service penetration through them fire-stopped and Q-Mark labelled, with staff briefed before work started and work areas barriered.
Outcome
Before-and-after completion packs for each office, handed over with the installation records.
Services used
Related projects
Fire-stopping survey and programmeEast Midlands
17-storey council tower
226locations pinned
18levels surveyed
A 226-location survey report and a 43-day phase-one programme: asbestos survey, two days' mobilisation and 36 days on the tools, working top down at 1.5 days per floor.
View project →Asbestos, then fire stoppingEast Midlands
Twin council tower blocks
875locations recorded
31floors
477 and 398 locations recorded, photographed and rated at 60 minutes, with full-building reports issued. The fire works never waited on a second contractor.
View project →Golden-thread fire-stopping recordEast Midlands
14-storey residential tower
14floors
60 minevery seal
A floor-by-floor report with “installed” against every pin, ready for the landlord's building safety case.