Asbestos work in Ireland: the HSA permit

Ireland has never had an asbestos licence like Great Britain's. Since 21 December 2025 it has a permit system instead, and it changes how asbestos work has to be planned.

What changed

The Safety, Health and Welfare at Work (Exposure to Asbestos) (Amendment) Regulations 2025, S.I. No. 632 of 2025, replaced the old notification with a permit. The employer submits the notification, a plan of work and a risk assessment to the Health and Safety Authority at least 10 days before work starts, and receives a permit number before anyone begins.

What it means for programmes

  • Asbestos found mid-programme now means a wait of at least 10 days for a permit.
  • Surveying before the programme starts, and lodging the permit application early, is the only way to avoid the stop.
  • The permit number needs to be available on site.

How we work in Ireland

From our base in Longford we survey first, prepare the plan of work and risk assessment, and lodge the permit application before the programme starts, so the fire-stopping and asbestos work run as one programme.